An alternative technique to the demolition of a prestressed concrete box-girder bridge: A case study

S.S.R. Pereira, M.D.C. Magalhaes, H. Gazzinelli

Abstract

This is a case study in which the partial collapse of a prestressed concrete box-girder bridge in Brazil happened only nine days after removing the supporting scaffolding. It is believed that the actual reinforcement longitudinal steel bars in the pile caps were underestimated. Although only part of the structure had collapsed, it was decided that the whole structure should be demolished. It was claimed that there was not available alternatives for ‘in situ’ structural recovery that would not compromise local traffic and safety precaution procedures. This paper presents an alternative technique for the bridge structural recovery. The application of this technique was possible because the prestressing process used unbonded pos-tensioned concrete, i.e. the sheaths were not filled with grout. The technique was based on the use of a weld torch to cut the tensioned strands in the box-girders methodically, unloading the pillars and foundations. Experimental tests were performed ‘in loco’ and proved to be effective and safe. The application of this suggested technique ‘in situ’ is believed to be an original contribution to the knowledge.
Source: openalex_inverted_index · Quality: baseline

Research context

OpenAlex topics: Structural Response to Dynamic Loads · Structural Behavior of Reinforced Concrete · Concrete Corrosion and Durability

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

References (3)

Show source-provided references
1. Behaviour of instrumented prestressed high performance concrete bridge girders10.1016/j.conbuildmat.2010.04.026 ↗
2. Transverse modeling of concrete box-girder for prediction of deck slab ultimate load capacity10.1061/(ASCE)BE.1943-5592.0000489 ↗
3. Desprotensão de um cabo de 27 cordoalhas de 15,2mm com as extremidades já cortadas