Reinforced concrete (RC) transfer slabs (or beams) are common support structures for high-rise or multi-use buildings. The structure serves as a new base for the upper zones and transfers considerable loads to the foundation; hence, the RC transfer slab necessitates a massive thickness design, as well as the use of high-strength material, and should be constructed without cracks. In this paper, the temperature rise of the massive RC transfer slab controlled by embedded cooling pipes was predicted by the Ansys program, and the numerical prediction was verified by recorded data of the temperature rise of the massive RC transfer slab. Regarding to the temperature rise, both prediction data and recorded data showed that, initially, the temperature at the bottom surface and the core of the RC transfer slab rose fast, resulting in a substantial temperature differential (20.4 oC) with the top surface, and, during the cooling stage, the top surface then retained heat and cooled more slowly than the bottom surface; moreover, the model fitted quite well with the measurement at the peak temperature. Regarding cooling pipe operation, within the first four days, it was recommended that the flow rate of 30 oC cooling water was set as high as 26.5 L/m (liters/minute), and this number was subsequently increased to 30 L/m when the temperature differential within the concrete peaked at 20 hours.
Source: openalex_inverted_index · Quality: baseline

Research context

OpenAlex topics: Concrete Properties and Behavior · Innovative concrete reinforcement materials · Concrete Corrosion and Durability

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

References (34)

Show source-provided references
1. American Concrete Institute, Mass concrete, (ACI207.1R), 1996.
2. Neville · 1997
3. American Concrete Institute, Report on early-age cracking: causes, measurement, and mitigation (ACI 231R), 2010.
4. American Concrete Institute, Specifications for structural concrete (ACI 301), 2016.
5. Florida Department of Transportation, Standard specifications for road and bridge construction (FDOT), 2010.
6. Qatar: Ministry of Environment, Qatar construction specifications (QCS), 2014.
7. Vietnam: Ministry of Construction, Mass concrete - code of practice of construction and acceptance (TCXDVN 305), 2004.
8. Impact of Climate on mock-up for mass concrete incorporating pozzolans10.1016/j.conbuildmat.2018.12.008 ↗
9. P.B. Bamforth, Control of cracking caused by restrained deformation in concrete, Construction industry Research and information association (CIRIA C 766, 2018.
10. Delayed ettringite formation: recent developments and future directions
11. The effect of pozzolans and slag on expansion of mortars cured at elevated temperature: part 1: expansive behaviour10.1016/S0008-8846(02)01066-9 ↗
12. Chapter 8 – Microscopic examination of deteriorated concrete
13. American Concrete Institute, Cooling and insulating systems for mass concrete (ACI 207.4R), 2005.
14. Temperature control
15. Japanese Concrete Institute, Guidelines for control of cracking of mass concrete (JCI), 2016.
16. Precise simulation of heat-flow coupling of pipe cooling in mass concrete10.3390/ma14185142 ↗
17. Stress and damage in concrete induced by pipe cooling at mesoscopic scale10.1177/1687814017690509 ↗
18. Chapter 17 – Pipe cooling of mass concrete
19. Research on thermal cracking control in mass concrete by using cooling pile system
20. distribution of thermal cracking risk surface zones in mass concrete using numerical simulation
21. The mathematical prediction model for temperature regime in the mass concrete block using the cooling pipe system
22. The effect of concrete block size on the formation of temperature field and cracking of an early age
23. Mass shotcrete wall construction and thermal control plan
24. Tattari · 2022
25. American Concrete Institute, Hot Weather Concreting (ACI 305), 1991.
26. Y. Suzuki, S. Harada, K. Maekawa, Y. Tsuji, Evaluation of adiabatic temperature.
27. Chapter 3 - Portland cement
28. Chapter 5 - Hydration, setting and hardening of portland cement
29. The effect of delayed ettringite formation and alkali-silica reaction on concrete microstructure
30. Actual temperature evolution of thick raft concrete foundations and cracking risk analysis
31. A comparative study of temperature of mass concrete placed in August and November based on on-site measurement
32. Mass concrete placement of the offshore wind turbine foundation: a statistical approach to optimize the use of fly ash and silica fume
33. Thermal crack control in mass concrete structure using an automated curing system10.1016/j.autcon.2014.04.014 ↗
34. Temperatures and stresses due to cement hydration on the R/C foundation of a wind tower – a case study10.1016/j.engstruct.2008.01.018 ↗