Optimal pavement management strategy development with a stochastic model and its practical application to Ugandan national roads
Source abstract
Abstract
This study examines the applicability to developing countries of a pavement management system (PMS) with less data (two-point) requirement to complement current practice. Due to limited capacity, many developing countries like Uganda have adopted a PMS after specified intervals regardless of deterioration rate (i.e. time-dependent policy). Maintenance planning based on deterioration rate (i.e. condition-dependent policy), as proposed, would be more ideal because pavement deterioration is stochastic. A PMS was developed using the Markov hazard model and then an empirical study was conducted for surveyed Ugandan national road network comparing both policies considering a basic plan and a fixed budget. A greedy algorithm was used to select sections for repair based on worst condition first (for time-dependent) or fastest deterioration first (for condition-dependent). A shift to the condition-dependent policy increased percentages of network in good and fair condition by 8.6% and 2.5%, respectively, and reduced percentages in poor and bad condition by 8.5% and 2.6%, respectively. Additionally, maintenance plans with and without preventive maintenance were compared considering a fixed budget. Preventive maintenance further increased percentage in good condition by 27.4% and reduced percentages in poor and bad condition by 11.6% and 4.2%, respectively, with a 53.5% reduction in life cycle costs.
Source: openalex_inverted_index · Quality: baseline
Research context
OpenAlex topics: Infrastructure Maintenance and Monitoring · Construction Project Management and Performance · Public-Private Partnership Projects
SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.
Affiliations
Graduate School of Engineering, Department of Urban Management, Kyoto University, Kyoto, Japan
References (46)
Show source-provided references
1. AASHTO (American Association of State Highway and Transport Officials) · 2012
2. AASHTO (American Association of State Highway and Transport Officials) · 2015
3. 10.1080/10298436.2014.99318510.1080/10298436.2014.993185 ↗
4. 10.1080/10298436.2015.103900610.1080/10298436.2015.1039006 ↗
5. Bank of Uganda, 2018. Annual Report; https://www.bou.or.ug/bou/bouwebsite/bouwebsitecontent/ publications/Annual_Reports/All/Bank-of-Uganda-Annual-Report-2018.pdf.
6. 10.1061/JPEODX.000000310.1061/JPEODX.0000003 ↗
7. FHWA (Federal Highway Administration), USDoT (US Department of Transportation), 2014. Vehicle Classification Manual; FHWA-HRT-13-091.
8. George, K.P, 2000. MDOT pavement management system: prediction models and feedback systems. Jackson, MS: Mississippi Department of Transportation, Report Number FHWA/MS-DOT-RD-00-119.
9. 10.1201/b1483510.1201/b14835 ↗
10. 10.1007/s12205-015-0375-310.1007/s12205-015-0375-3 ↗
11. Han D. · KSCE Journal of Civil Engineering · 2017 · 21 · 174710.1007/s12205-016-1461-x ↗
12. 10.1007/s12205-012-0070-610.1007/s12205-012-0070-6 ↗
13. 10.1093/biomet/57.1.9710.1093/biomet/57.1.97 ↗
14. Hillier F.S. · 1990
15. Isaacson D.L. · 1976
16. JICA (Japan International Cooperation Agency), 2015. District and urban roads (DUR) mapping and roads database Project in the Republic of Uganda: Project Completion Report.
17. Kaito K. · Journal of Japan Society of Civil Engineers · 2015 · 71 · 1
18. Kerali, H. R., and Snaith, M. S., 1992. NETCOM: the TRL visual condition model for road networks. Crowthorne: Transport Research Laboratory, Contractor Report No. 921.
19. Kobayashi K. · Journal of Japan Society of Civil Engineers · 2013 · 1 · 551
20. 10.1007/s12205-010-0343-x10.1007/s12205-010-0343-x ↗
21. 10.1016/j.trb.2011.11.00810.1016/j.trb.2011.11.008 ↗
22. 10.7492/IJAEC.2012.00110.7492/IJAEC.2012.001 ↗
23. 10.1017/CCOL052126596710.1017/CCOL0521265967 ↗
24. Lethanh N. · International Journal of Civil and Environmental Engineering · 2012 · 6 · 7
25. 10.1061/(ASCE)IS.1943-555X.000024210.1061/(ASCE)IS.1943-555X.0000242 ↗
26. 10.1139/l97-00110.1139/l97-001 ↗
27. 10.1016/S0965-8564(01)00020-910.1016/S0965-8564(01)00020-9 ↗
28. 10.1287/trsc.28.1.5510.1287/trsc.28.1.55 ↗
29. 10.1061/JPEODX.000013810.1061/JPEODX.0000138 ↗
30. MoWT (Ministry of Works and Transport) – Uganda · 2010
31. MoWT (Ministry of Works and Transport) – Uganda, 2011–2017. Annual Sector Performance Reports (ASPR); http://www.works.go.ug/document-category/jtsrw/.
32. MoWT (Ministry of Works and Transport) – Uganda · 2015
33. 10.1061/(ASCE)0733-947X(2006)132:2(141)10.1061/(ASCE)0733-947X(2006)132:2(141) ↗
34. Oxford Economics, 2014. Capital project and infrastructure spending Outlook to 2025. Available from: https://www.pwc.com/gx/en/capital-projects-infrastructure/publications/cpi-outlook/assets/cpi-outlook-to-2025.pdf.
35. Pantuso A. · International Journal of Pavement Engineering · 2019
36. 10.1080/10298436.2017.135339010.1080/10298436.2017.1353390 ↗
37. 10.3390/coatings1002009710.3390/coatings10020097 ↗
38. 10.1007/s40999-017-0254-z10.1007/s40999-017-0254-z ↗
39. 10.1016/0166-218X(93)90051-O10.1016/0166-218X(93)90051-O ↗
40. Saha P. · Journal of Advanced Transportation · 2017 · 2017 · 110.1155/2017/9474838 ↗
41. Sundaram R.K · 1999
42. 10.3141/2366-0410.3141/2366-04 ↗
43. 10.2208/jsceseee.23.241s10.2208/jsceseee.23.241s ↗
44. Tsunokawa K. · Transport Research · 1994 · 28 · 151
45. Uddin W · 2006 · 18-1
46. UNRA (Uganda National Roads Authority), 2019. Database (Available on request from UNRA).