Profit Optimization in Multi-Unit Construction Projects Under Variable Weather Conditions: A Wind Farm Case Study
Source abstract
Abstract
This paper introduces a novel scheduling model that integrates weather-based productivity coefficients into multi-unit construction projects, aiming to enhance profit and reduce delays. The method is suitable especially for renewable energy, open-area projects. The authors propose a flow-shop optimization framework that considers key aspects of construction contracts, e.g., contractual penalties, downtime losses, and cash flow constraints. A proprietary Tabu Search (TS) metaheuristic algorithm variant is used to solve the resulting NP-hard problem. Numerical experiments on multiple test sets indicate that the TS algorithm consistently outperforms other methods in finding higher-profit schedules. A real-world wind farm case study further demonstrates substantial improvements, transforming an initially loss-making operation into a profitable venture. By explicitly accounting for weather disruptions within a formalized scheduling model, this work advances the understanding of reliable project planning under uncertain environmental conditions. The solution framework offers contractors an effective tool for mitigating scheduling risks and optimizing resource usage. The integration of weather data and cash flow management increases the likelihood of on-time and on-budget project delivery.
Source: crossref · Quality: baseline
Research context
OpenAlex topics: Resource-Constrained Project Scheduling · BIM and Construction Integration · Construction Project Management and Performance
SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.
Affiliations
Faculty of Civil Engineering, Wrocław University of Science and Technology, 50-370 Wrocław, Poland
Faculty of Civil Engineering, Warsaw University of Technology, 00-637 Warszawa, Poland
Faculty of Civil Engineering, Cracow University of Technology, 31-155 Kraków, Poland
References (47)
Show source-provided references
1. Cost optimization of multiunit construction projects using linear programming and metaheuristic-based simulated annealing algorithm10.3846/jcem.2019.11308 ↗
2. Harmonizing construction processes in repetitive construction projects with multiple buildings10.1016/j.autcon.2022.104266 ↗
3. Customized particle swarm optimization for harmonizing multi-section construction projects10.1016/j.autcon.2024.105359 ↗
4. Profit optimization for multi-mode repetitive construction project with cash flows using metaheuristics10.1007/s43452-021-00218-2 ↗
5. Podolski, M., Rosłon, J., and Sroka, B. (2022). The impact of the learning and forgetting effect on the cost of a multi-unit construction project with the use of the simulated annealing algorithm. Appl. Sci., 12.10.3390/app122412667 ↗
6. Flowshop scheduling research after five decades10.1016/j.ejor.2005.02.001 ↗
7. Weather and labor productivity in construction: A literature review and taxonomy of studies
8. Weather-wise: A weather-aware planning tool for improving construction productivity and dealing with claims10.1016/j.autcon.2017.08.022 ↗
9. Estimating weather impact on the duration of construction activities10.1139/l96-122 ↗
10. Simulation modeling of weather-sensitive tunnelling construction activities subject to cold weather10.1139/cjce-2013-0087 ↗
11. AACE® International (2010). Schedule Levels of Detail-As Applied in Engineering, Procurement, and Construction, AACE® International. AACE® International Recommended Practice No. 37R-06.
12. Fuzzy duration forecast model for wind turbine construction project subject to the impact of wind uncertainty10.1016/j.autcon.2017.03.009 ↗
13. Atef, D., Osman, H., Ibrahim, M., and Nassar, K. (2010, January 5–8). A Simulation-Based Planning System for Wind Turbine Construction. Proceedings of the 2010 Winter Simulation Conference, Baltimore, MD, USA.10.1109/WSC.2010.5679020 ↗
14. Stochastic resource-constrained project scheduling problem with time varying weather conditions and an improved estimation of distribution algorithm10.1016/j.cie.2021.107322 ↗
15. Mohamed, E., Jafari, P., Chehouri, A., and AbouRizk, S. (2021). Simulation-Based Approach for Lookahead Scheduling of Onshore Wind Projects Subject to Weather Risk. Sustainability, 13.10.3390/su131810060 ↗
16. Management of resources in multiunit construction projects with the use of a tabu search algorithm10.3846/13923730.2015.1073616 ↗
17. A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction10.1515/eng-2019-0006 ↗
18. Combined discrete-event/continuous simulation for project planning10.1061/(ASCE)0733-9364(1997)123:1(11) ↗
19. Impact of rainfall on the productivity of highway construction10.1061/(ASCE)0733-9364(2001)127:2(125) ↗
20. A fuzzy approach to construction project risk assessment and analysis: Construction project risk management system10.1016/S0965-9978(01)00036-9 ↗
21. Quantifying weather impact on formwork shuttering and removal operation using system dynamics10.1007/s12205-013-0301-5 ↗
22. Automated tool for predicting duration of construction activities in tropical countries10.1007/s12205-015-0263-x ↗
23. Time-Profit Trade-Off of Construction Projects Under Extreme Weather Conditions
24. Multiobjective optimization model for scheduling of construction projects under extreme weather10.3846/13923730.2014.897968 ↗
25. Impact of weather conditions10.1504/MEJM.2018.088734 ↗
26. Survey of the construction industry relative to the use of CPM scheduling for construction projects10.1061/(ASCE)0733-9364(2006)132:7(697) ↗
27. Challenges in line-of-balance scheduling10.1061/(ASCE)0733-9364(2002)128:6(545) ↗
28. Comparison of linear scheduling model and repetitive scheduling method10.1061/(ASCE)0733-9364(2003)129:1(56) ↗
29. The application of time coupling methods in the engineering of construction projects
30. Scheduling repetitive construction projects: Structured literature review10.3846/jcem.2022.16943 ↗
31. Applying metaheuristic strategies in construction projects management10.3846/13923730.2012.719837 ↗
32. Flowshop scheduling of construction processes with uncertain parameters10.1016/j.acme.2018.09.010 ↗
33. The association analysis for risk evaluation of significant delay occurrence in the completion date of construction project10.1007/s13762-018-1892-7 ↗
34. Legal perspective on treatment of delay liquidated damages and penalty clauses by different jurisdictions: Comparative analysis10.1061/(ASCE)LA.1943-4170.0000387 ↗
35. Optimization and approximation in deterministic sequencing and scheduling: A survey10.1016/S0167-5060(08)70356-X ↗
36. Tabu search—Part I10.1287/ijoc.1.3.190 ↗
37. Tabu search—Part II10.1287/ijoc.2.1.4 ↗
38. Wind turbine power curve modeling using radial basis function neural networks and tabu search10.1016/j.renene.2020.10.020 ↗
39. An image encryption algorithm based on Tabu Search and hyperchaos10.1142/S0218127424501700 ↗
40. A hybrid genetic algorithm and tabu search for minimizing makespan in flow shop scheduling problem10.1016/j.jksuci.2021.08.025 ↗
41. Bartz-Beielstein, T., Chiarandini, M., Paquete, L., and Preuss, M. (2010). Experimental Methods for the Analysis of Optimization Algorithms, Springer. [1st ed.].10.1007/978-3-642-02538-9 ↗
42. Random Search Techniques for Optimization Problems10.1016/0005-1098(63)90018-9 ↗
43. Some efficient heuristic methods for the flow shop sequencing problem10.1016/0377-2217(90)90090-X ↗
44. Optimization by simulated annealing10.1126/science.220.4598.671 ↗
45. The application of the simulated annealing algorithm to the solution of the n/m/Cmax flowshop problem10.1016/0305-0548(90)90001-N ↗
46. Lorenc, H. (2005). Atlas klimatu Polski (Eng. Polish Climate Atlas), IMGW.
47. Kulejewski, J., Ibadov, N., Rosłon, J., and Zawistowski, J. (2021). Cash flow optimization for renewable energy construction projects with a new approach to critical chain scheduling. Energies, 14.10.3390/en14185795 ↗