Sigmoidal Mathematical Models in the Planning and Control of Rigid Pavement Works

Jose Manuel Palomino Ojeda, Lenin Quiñones Huatangari, Billy Alexis Cayatopa Calderon, Manuel Emilio Milla Pino, José Luis Piedra Tineo, Marco Antonio Martínez Serrano, Rosario Yaqueliny Llauce Santamaria

Applied Sciences· Volume 15· Issue 15

Abstract

The objective of the research was to use sigmoidal mathematical models for the planning and control of rigid pavement works. A dataset was constructed using 140 technical files, which were then analyzed to extract the valued work schedules. These schedules contained the variables time and cost per month. Subsequently, two groups were created from the dataset: a training group comprising 80% of the data and a test group comprising the remaining 20%. Subsequently, the variables were normalized and adjusted with the proposed logistic, Von Bertalanffy, and Gompertz models using Python 3.11.13. Following the implementation of training and validation procedures, the logistic model was identified as the optimal fit, as indicated by the following metrics: R2 = 0.9848, MSE = 0.0026, RMSE = 0.0506, and MAE = 0.0278. The implementation of the aforementioned model facilitates the establishment of an early warning system with a high degree of effectiveness. This system enables the evaluation of the discrepancy between the actual progress and the planned progress with an R2 greater than 98%, thereby serving as a robust instrument for the adjustment and revalidation of activities before and following their execution.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: BIM and Construction Integration

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Seismological and Construction Research Institute, National University of Jaen, Jaen 06800, Peru

Instituto de Investigacion en Estudios Estadisticos y Control de Calidad, Facultad de Ingenieria Zootecnista, Biotecnologia, Agronegocios y Ciencia de Datos, Universidad Nacional Toribio Rodriguez de Mendoza de Amazonas, Chachapoyas 01001, Peru

Department of Civil Engineering, Faculty of Engineering, National University of Jaen, Jaen 06800, Peru

Academic Department of Basic and Applied Sciences, National University of Jaen, Jaen 06800, Peru

References (41)

Show source-provided references
1. Evaluation of Risk Factors Causing Cost Overrun in Road Projects in Terrorism Affected Areas Pakistan—A Case Study10.1007/s12205-015-0348-6 ↗
2. Planning and Design Models for Construction Industry: A Critical Survey10.1016/j.autcon.2011.09.011 ↗
3. A Case Study of Activity-Based Costing in Allocating Rebar Fabrication Costs to Projects10.1080/01446193.2011.570354 ↗
4. Voigtmann, J., and Bargstädt, H.-J. (2010, January 5–8). Construction Logistics Planning by Simulation. Proceedings of the 2010 Winter Simulation Conference, Baltimore, MD, USA.10.1109/WSC.2010.5679012 ↗
5. The S-Curve Envelope as a Tool for Monitoring and Control of Projects10.1016/j.procs.2017.11.097 ↗
6. Developing Cost Estimation Models for Road Rehabilitation and Reconstruction: Case Study of Projects in Europe and Central Asia10.1061/(ASCE)CO.1943-7862.0000817 ↗
7. Developing a Mathematical Model for Planning Repetitive Construction Projects by Using Support Vector Machine Technique10.2478/cee-2021-0039 ↗
8. Hsieh, T.-Y., Wang, M.H.-L., Chen, C.-W., Tsai, C.-H., and Yu, S.-E. (2025, March 05). Fuzzy-Model-Based S-Curve Regression for Working Capital Construction Management with Statistical Method. Available online: https://citeseerx.ist.psu.edu/document?repid=rep1&type=pdf&doi=4c2adb8879403bf7ea87951ba7ee115e6e1de33e.
9. RazaviAlavi, S., and AbouRizk, S. (2021). Construction Site Layout Planning Using a Simulation-Based Decision Support Tool. Logistics, 5.10.3390/logistics5040065 ↗
10. The S-Curve Relation Between Per-Capita Income and Insurance Penetration10.1111/1468-0440.00072 ↗
11. The S-curve for forecasting waste generation in construction projects10.1016/j.wasman.2016.07.039 ↗
12. Automating Road Construction Planning with a Specific-Domain Simulation System
13. New Viewpoint of S-Curve Regression Model and Its Application to Construction Management10.1142/S021821300600259X ↗
14. Estimating Project S-Curves Using Polynomial Function and Neural Networks10.1061/(ASCE)0733-9364(2009)135:3(169) ↗
15. Szóstak, M. (2022). Best Fit of Cumulative Cost Curves at the Planning and Performed Stages of Construction Projects. Buildings, 13.10.3390/buildings13010013 ↗
16. A Model for Updating Project S-Curve by Using Neural Networks and Matching Progress10.1016/j.autcon.2009.09.006 ↗
17. A Method for Forecasting Owner Monthly Construction Project Expenditure Flow10.1016/S0169-2070(97)00042-3 ↗
18. A Construction Project Net Cash Flow Model10.1080/01446198900000002 ↗
19. Time Prediction Using a Neuro-Fuzzy Model for Projects in the Construction Industry
20. Applying Building Information Modeling to Integrate Schedule and Cost for Establishing Construction Progress Curves10.1016/j.autcon.2016.10.005 ↗
21. An Innovative Approach for Generation of a Time Location Plan in Road Construction Projects10.1080/01446193.2011.563785 ↗
22. Shu, S., Zhuang, C., Ren, R., Xing, B., Chen, K., and Li, G. (2022). Effect of Different Anti-Stripping Agents on the Rheological Properties of Asphalt. Coatings, 12.10.3390/coatings12121895 ↗
23. Sepaskhah, A.R., and Mazaheri-Tehrani, M. (2024). A Sigmoidal Model for Predicting Soil Thermal Conductivity-Water Content Function in Room Temperature. Sci. Rep., 14.10.1038/s41598-024-68455-y ↗
24. Modeling Approach for the Parameters of Von Bertalanffy Growth Equation10.1007/s40314-024-02591-z ↗
25. On the Exponent in the Von Bertalanffy Growth Model10.7717/peerj.4205 ↗
26. Some New Results of a Fractional Von Bertalanffy Model
27. Vilanova, A., Kim, B.-Y., Kim, C.K., and Kim, H.-G. (2020). Linear-Gompertz Model-Based Regression of Photovoltaic Power Generation by Satellite Imagery-Based Solar Irradiance. Energies, 13.10.3390/en13040781 ↗
28. Mathematical Modeling of Three-Dimensional Genetic Regulatory Networks Using Logistic and Gompertz Functions10.37394/23203.2022.17.12 ↗
29. Discrete Gompertz Equation and Model Selection Between Gompertz and Logistic Models10.1016/j.ijforecast.2021.01.005 ↗
30. Zhou, B., Yan, Y., and Kang, J. (2023). Dynamic Prediction Model for Progressive Surface Subsidence Based on MMF Time Function. Appl. Sci., 13.10.3390/app13148066 ↗
31. Predicting Construction Cost and Schedule Success Using Artificial Neural Networks Ensemble and Support Vector Machines Classification Models10.1016/j.ijproman.2011.09.002 ↗
32. Integrated Design and Construction Planning System for Computer Integrated Construction10.1016/0926-5805(92)90033-G ↗
33. Genetic Algorithm for Determining the Construction Logistics of Precast Components10.1108/ECAM-09-2018-0386 ↗
34. Logistics Optimisation in Road Construction Project10.1108/CI-03-2016-0014 ↗
35. Model for Construction Budget Performance—Neural Network Approach10.1061/(ASCE)0733-9364(1997)123:3(214) ↗
36. Short-Interval Dynamic Forecasting for Actual S-Curve in the Construction Phase10.1061/(ASCE)CO.1943-7862.0000358 ↗
37. Construction Project Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical Models and Critical Path Method10.1061/(ASCE)0733-9364(2009)135:10(1096) ↗
38. Planning the time and cost of implementing construction projects using an example of residential buildings
39. S-curve modeling in early phases of construction projects
40. Integrated project delivery with BIM: An automated EVM-based approach10.1016/j.autcon.2019.102907 ↗
41. A fixed start scheduling approach for repetitive construction projects10.1007/s12205-020-1429-8 ↗