Updating Financial Contingency in Execution of Typologically Diverse Construction Projects

Tomasz Stachoń, Mariusz Szóstak, Jarosław Konior

Applied Sciences· Volume 15· Issue 8

Abstract

The article presents research findings on updating financial contingency estimates for typologically diverse construction projects. The research was carried out from 2006 to 2024 on a sample of 41 investment tasks, represented by five different construction sectors, in which 547 measurements were made of the deviation of the earned cost of construction works from its planned values. The study found significant variability in the cost performance index (CPI) across different construction types. Box plots were determined, and their statistical interpretation made it possible to determine the actual financial contingency, the variation in which in the groups of residential, office and hotel buildings, as well as shopping and logistics centres, is in the range of 3% to 30%. The article concludes with recommendations for banks financing investment tasks in the direction of making financial contingency more realistic when making sustainable lending decisions.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Construction Project Management and Performance · Construction Management and Sustainability · BIM and Construction Integration

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Department of General Construction, Faculty of Civil Engineering, Wroclaw University of Science and Technology, 50-370 Wrocław, Poland

References (44)

Show source-provided references
1. Tijanić, K., and Car-Pušić, D. (2017, January 27–30). Application of S-Curve in EVA Method. Proceedings of the 13th International Conference “Organization, Technology and Management in Construction”, Poreč, Croatia.
2. Project Management Institute (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide), Project Management Institute (PMI). [6th ed.].
3. IPMA (2015). IPMA Individual Competence Baseline, IPMA.
4. Abba, W.F. (2000, January 7–16). How Earned Value Got to Primetime: A Short Look Back and Glance Ahead. Proceedings of the Project Management Institute Annual Seminars & Symposium, Houston, TX, USA.
5. Earned Value-Based Performance Monitoring of Facility Construction Projects10.1108/14725961311301475 ↗
6. Monitoring Production Time and Cost Performance by Combining Earned Value Analysis and Adaptive Fuzzy Control10.1016/j.cie.2018.11.019 ↗
7. Earned Value Project Management: Improving the Predictive Power of Planned Value10.1016/j.ijproman.2015.09.008 ↗
8. Cost Controlling Using Earned Value Analysis in Construction Industries
9. The Cost Monitoring of Construction Projects through Earned Value Analysis
10. Szóstak, M., Stachoń, T., and Konior, J. (2024). Course of Cumulative Cost Curve (CCCC) as a Method of CAPEX Prediction in Selected Construction Projects. Appl. Sci., 14.10.3390/app14135597 ↗
11. Duration and Cost Variability of Construction Activities: An Empirical Study10.1061/(ASCE)CO.1943-7862.0001739 ↗
12. Przywara, D., and Rak, A. (2021). Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Appl. Sci., 11.10.3390/app11041357 ↗
13. Plebankiewicz, E. (2018). Model of Predicting Cost Overrun in Construction Projects. Sustainability, 10.10.3390/su10124387 ↗
14. Konior, J., and Szóstak, M. (2020). The S-Curve as a Tool for Planning and Controlling of Construction Process-Case Study. Appl. Sci., 10.10.3390/app10062071 ↗
15. Monitoring of Construction Projects Feasibility by Bank Investment Supervision Approach10.13189/cea.2019.070105 ↗
16. Shah, F.H., Bhatti, O.S., and Ahmed, S. (2023). A Review of the Effects of Project Management Practices on Cost Overrun in Construction Projects †. Eng. Proc., 44.10.3390/engproc2023044001 ↗
17. Assessing the Risk Perception of Cost Overrun through Importance Rating10.3846/20294913.2017.1321053 ↗
18. Investigation of Critical Factors Affecting Cost Overruns and Delays in Egyptian Megaconstruction Projects10.1016/j.aej.2023.10.052 ↗
19. Effective Control Measures to Minimize Cost Overrun during Construction Phase of High-Rise Residential Building Projects in Chongqing, China
20. The Potential of New Models of Construction Procurement to Counter Cost Overruns in Construction Projects: An Exploratory Study from a Contractors’ Perspective10.1108/JFMPC-08-2022-0035 ↗
21. Risk Factors Causing Cost Overruns in Road Networks10.1016/j.asej.2022.101720 ↗
22. Sharma, S., and Gupta, A.K. (2021). Analysis of Factors Affecting Cost and Time Overruns in Construction Projects. Advances in Geotechnics and Structural Engineering: Select Proceedings of TRACE 2020, Springer. Lecture Notes in Civil Engineering.10.1007/978-981-33-6969-6_6 ↗
23. Alhammadi, Y., Al-Mohammad, M.S., and Rahman, R.A. (2024). Modeling the Causes and Mitigation Measures for Cost Overruns in Building Construction: The Case of Higher Education Projects. Buildings, 14.10.3390/buildings14020487 ↗
24. Memon, A.H., Rahman, I.A., and Aziz, A.A.A. (2015, January 11–12). Study of Causative Factors of Cost Overrun in Large Projects of Southern Part of Peninsular Malaysia. Proceedings of the 26th International Business Information Management Association Conference—Innovation Management and Sustainable Economic Competitive Advantage: From Regional Development to Global Growth, IBIMA 2015, Madrid, Spain.
25. Ezeldin, A.S., and Ali, G.G. (2017, January 26–28). Cash Flow Optimization for Construction Portfolios. Proceedings of the International Conference on Sustainable Infrastructure 2017: Policy, Finance, and Education, New York, NY, USA.10.1061/9780784481202.003 ↗
26. Mitigation of correlated risk in construction projects10.13189/cea.2019.070103 ↗
27. Konior, J., and Szóstak, M. (2021). Time and Cost Variance of Construction Projects Monitored by Bank Investment Supervision. International Scientific Conference Environmental Challenges in Civil Engineering, Springer International Publishing.10.1007/978-3-030-63879-5_16 ↗
28. PM Group Polska sp. z o.o. 2006–2015 and 3EPCM sp. z o.o. 2016–2024. “Initial, Monthly, Close-out Reporting of Bank Investment Supervision”.
29. (2025, February 20). Regulation of the Council of Ministers of 30 December 1999 on the Polish Classification of Building Structures (PKOB) (Decree from 1999 r. No 112, Item. 1316), Available online: https://isap.sejm.gov.pl/isap.nsf/DocDetails.xsp?id=WDU19991121316.
30. Wickham, H., and Stryjewski, L. (2025, February 20). 40 Years of Boxplots. Had.Co.Nz 2011. Available online: https://vita.had.co.nz/papers/boxplots.pdf.
31. Categorization of Potential Project Cost Overrun Factors in Construction Industry10.1088/1755-1315/140/1/012098 ↗
32. Cost Overruns of Public Sector Construction Projects: A Developing Country Perspective10.1108/IJMPB-09-2018-0177 ↗
33. Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects10.1061/(ASCE)ME.1943-5479.0000391 ↗
34. A System Dynamics Model for Assessing the Impacts of Design Errors in Construction Projects10.1016/j.mcm.2011.06.039 ↗
35. Project Pathogens: The Anatomy of Omission Errors in Construction and Resource Engineering Project10.1109/TEM.2008.927774 ↗
36. Factors Affecting Cost Overruns in Micro-Scaled Construction Companies10.1016/j.proeng.2014.10.569 ↗
37. Design Changes in Construction Projects—Causes and Impact on the Cost10.28991/cej-2019-03091360 ↗
38. Cost Overrun in Construction Projects in Developing Countries, Gas-Oil Industry of Iran as a Case Study10.3846/13923730.2014.992467 ↗
39. Ranking of the Factors Causing Cost Overrun in Infrastructural Projects of Uae
40. Ameliorating Time and Cost Control with Project Learning and Communication Management: Leveraging on Reusable Knowledge Assets10.1108/IJMPB-02-2019-0034 ↗
41. Data Exploration on Factors That Influences Construction Cost and Time Performance on Construction Project Sites10.1016/j.dib.2018.02.035 ↗
42. Multiobjective Optimization Model for Scheduling of Construction Projects under Extreme Weather10.3846/13923730.2014.897968 ↗
43. Przywara, D., and Rak, A. (2018, January 18). Analysis Construction Industry on the Basis of Price Trends of Labor Cost. Proceedings of the MATEC Web of Conferences, Bandung, Indonesia.10.1051/matecconf/201817404005 ↗
44. Przywara, D., and Rak, A. (2023). Economic Conditions of Leaving the Construction Site by the Contractor at Different Stages of Its Implementation. Environmental Challenges in Civil Engineering II, Springer. Lecture Notes in Civil Engineering.10.1007/978-3-031-26879-3_24 ↗