Construction Schedule versus Various Constraints and Risks

Paulina Kostrzewa-Demczuk

Applied Sciences· Volume 14· Issue 1

Abstract

The organization and planning of construction works are difficult issues due to the complexity, numerous limitations, uncertainty and risks associated with them. Construction planning is usually based on deterministic data. However, numerous studies and analyses of real cases show that a different computational approach is needed—one based on probabilistic data. The computational algorithms of the Time Coupling Method make it possible to introduce probabilistic data generated in the Multivariate Method of Statistical Models (MMSM) and via standard deviations. As a result, a new methodology was created, the Probabilistic Time Coupling Method (PTCM), through which it is possible to obtain a very good forecast of the investment implementation time compared to its real time. The paper presents theoretical considerations, computational schemes and validation exercises of this new method—known as the PTCM. The computational results of the PTCM (with a mapping accuracy prediction of 99%) confirm the effectiveness of the method. The computational algorithms of the PTCM enable the creation of a computational application based on a well-known program, e.g., Microsoft Excel, thanks to which the method can be quickly disseminated in the planning environment and widely used.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: BIM and Construction Integration · Construction Project Management and Performance · Probabilistic and Robust Engineering Design

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Department of Building Engineering Technologies and Organization, Faculty of Civil Engineering and Architecture, Kielce University of Technology, al. Tysiąclecia PP 7, 25-314 Kielce, Poland

Funding

Paulina Kostrzewa-Demczuk

References (62)

Show source-provided references
1. An efficient method for scheduling construction projects with resource constraints10.1016/S0263-7863(00)00024-7 ↗
2. Ameen, M., and Jacob, M. (2007). Complexity in Projects. A Study of Practitioners’ Understanding of Complexity in Relation to Existing Theoretical Models. [Master’s Thesis, Umea School of Business].
3. Evaluating construction project complexity
4. Project complexity indicators and management strategies—A Delphi study10.1016/j.proeng.2016.04.048 ↗
5. Urgiles, P., Sebastian, M.A., and Claver, J. (2020). Proposal and Application of a Methodology to Improve the Control and Monitoring of Complex Hydroelectric Power Station Construction Projects. Appl. Sci., 10.10.3390/app10217913 ↗
6. Agyekum-Mensah, G., Knight, A., and Pasquire, C. (2012, January 3–5). Adaption of structured analysis design techniques methodology for construction project planning. Proceedings of the 28th Annual ARCOM Conference, ARCOM, Edinburgh, UK.
7. Should we build more large dams? The actual costs of hydropower megaproject development10.1016/j.enpol.2013.10.069 ↗
8. Were the hydro dams financed by the World Bank from 1976 to 2005 worthwhile?10.1016/j.enpol.2015.06.040 ↗
9. The S-curve envelope as a tool for monitoring and control of projects10.1016/j.procs.2017.11.097 ↗
10. An international comparative assessment of construction cost overruns for electricity infrastructure10.1016/j.erss.2014.07.016 ↗
11. Delays in construction projects: The case of Jordan10.1016/j.ijproman.2007.09.009 ↗
12. Analiza skuteczności wykonania harmonogramu robót za pomocą Katalogów Nakładów Rzeczowych
13. Liu, N., Kang, B.G., and Zheng, Y. (2018, January 4). Current trend in planning and scheduling of construction project using artificial in telligence. Proceedings of the IET Doctoral Forum on Biomedical Engineering, Healthcare, Robotics and Artificial Intelligence 2018 (BRAIN 2018), Ningbo, China.
14. Nusen, P., Boonyung, W., Nusen, S., Panuwatwanich, K., Champrasert, P., and Kaewmoracharoen, M. (2021). Construction planning and scheduling of a renovation project using BIM-based multi-objective genetic algorithm. Appl. Sci., 11, Available online: https://ssrn.com/abstract=4616055.10.3390/app11114716 ↗
15. Artificial Intelligence Technology Based on Deep Learning in Building Construction Management System Modeling
16. Artificial intelligence in the construction industry: A review of present status, opportunities and future challenges10.1016/j.jobe.2021.103299 ↗
17. Doukari, O., Seck, B., and Greenwood, D. (2022). The creation of construction schedules in 4D BIM: A comparison of conventional and automated approaches. Buildings, 12.10.3390/buildings12081145 ↗
18. Real-time pipe system installation schedule generation and optimization using artificial intelligence and heuristic techniques
19. A BIM-based framework for construction project scheduling risk management10.1504/IJCAET.2020.105575 ↗
20. Zhang, L., Pan, Y., Wu, X., and Skibniewski, M.J. (2021). Artificial Intelligence in Construction Engineering and Management, Springer.10.1007/978-981-16-2842-9 ↗
21. Potentials of artificial intelligence in construction management
22. Chen, H.-P., and Ying, K.-C. (2022). Artificial Intelligence in the Construction Industry: Main Development Trajectories and Future Outlook. Appl. Sci., 12.10.3390/app12125832 ↗
23. Kowalczyk, Z., and Zabielski, J. (2012). Kosztorysowanie i Normowanie w Budownictwie, WSiP.
24. Hoła, B., and Mrozowicz, J. (2003). Modelowanie Procesów Budowlanych o Charakterze Losowym, DWE.
25. Rogalska, M. (2016). Wieloczynnikowe Modele w Prognozowaniu Czasu Procesów Budowlanych, Monografie.
26. PMI (2017). A Guide to the Project Management Body of Knowledge, Project Management Institute (PMI).
27. An assessment of risk impact on road projects in Osun State, Nigeria10.1108/BEPAM-04-2019-0040 ↗
28. Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines10.1061/(ASCE)CO.1943-7862.0000857 ↗
29. Impacts of synergies on software project scheduling
30. A Big Data and FMEA-based construction quality risk evaluation model considering project schedule for Shanghai apartment projects10.1108/IJQRM-11-2018-0318 ↗
31. A review of fuzzy risk assessment models for construction projects10.2478/v10189-012-0016-5 ↗
32. Hulett, D. (2009). Practical Schedule Risk Analysis, Ashgate Publishing Group.
33. Knosala, R. (2014). Innowacje w zarządzaniu i inżynierii produkcji, Tom 1, Oficyna Wydawnicza Polskiego Towarzystwa Zarządzania Produkcją.
34. Marcinkowski, R. (2002). Metody Rozdziału Zasobów Realizatora w Działalności Inżynieryjno–Budowlanej, WAT.
35. Causes and effects of delays in Malaysian construction industry10.1016/j.ijproman.2006.11.007 ↗
36. Afanasev, V.A., and Afanasev, A.V. (2000). Potocnaja Organizacja Rabot v Stroitelstwie.
37. Jaworski, K.M. (1999). Metodologia Projektowania Realizacji Budowy, Wydawnictwo Naukowe PWN.
38. Planning repetitive construction: Current practice10.1080/01446199300000003 ↗
39. Sprzężenia czasowe w metodach organizacji złożonych procesów budowlanych
40. Teoria szeregowania zadań a metody sprzężeń czasowych
41. Mrozowicz, J. (1997). Metody Organizacji Procesów Budowlanych Uwzględniające Sprzężenia Czasowe, Dolnośląskie Wyd, Edukacyjne.
42. Podolski, M. (2008). Analiza nowych zastosowań teorii szeregowania zadań w organizacji robót budowlanych. [Ph.D. Thesis, Wrocław University of Technology].
43. Afanasejv, V.A. (1980). Algoritmy Formirovania Rascieta i Optimizacji Metod Organizacji Rabot, Ucziebnoje pasobije.
44. Afanasev, V.A., and Afanasev, A.V. (1985). Paralelno–Potočnaja Organizacja Stroitelstva, LISI.
45. Afanasev, V.A., and Afanasev, A.V. (1988). Projektirowanije Organizacji Stroitielstva, Organizacji i Proizvodstwa Rabot, LISI.
46. Afanasev, V.A. (1994). Učiet Zatrat Wremieni Na Perieboizirowanije Stroitielnych Organizacji Pri Formirowani I Optimalizacji Kompleksov Potokov, Aktualnyje problemy sovietskowo stroitielstwa.
47. Mrozowicz, J. (1982). Potokowe Metody Organizacji Procesów Budowlanych o Charakterze Deterministycznym. [DSc. Thesis, Wyd. Politechniki Wrocławskiej]. Monografia no 14.
48. Hejducki, Z. (2004). Zarządzanie Czasem w Procesach Budowlanych z Zastosowaniem Modeli Macierzowych, Wydawnictwo Politechniki Wrocławskiej.
49. Sequencing problems in methods of organising construction processes10.1108/09699980410512638 ↗
50. Hejducki, Z., and Rogalska, M. (2021). Flow Shop Scheduling of Construction Prosesses Using Time Coupling Methods, Politechnika Lubelska.
51. Rogalska, M., and Hejducki, Z. (2011). Organizacja Przedsięwzięć Budownictwa Drogowego/Red. Nauk. Zbigniew Tokarski, Zarząd Oddziału Stowarzyszenia Inżynierów i Techników Komunikacji RP.
52. Rogalska, M., and Hejducki, Z. (2011). Organizacja Przedsięwzięć Budownictwa Drogowego/Red. Nauk. Zbigniew Tokarski, Zarząd Oddziału Stowarzyszenia Inżynierów i Techników Komunikacji RP.
53. Rogalska, M., Hejducki, Z., and Wodecki, M. (2014, January 20–21). Development of time couplings method. Proceedings of the International Scientific Conference in Posthumous Memory of Professor Viktor Alekseevic Afanas’ev, Sankt-Peterburg, Russia.
54. Scheduling with the Probabilistic Coupling Method I (PTCM I)–assuming the continuity of workof working teams
55. Scheduling construction processes using the probabilistic time coupling method III
56. Hejducki, Z., and Rogalska, M. (2011). Time Coupling Methods: Construction Scheduling and Time/Cost Optimization, Oficyna Wydawnicza Politechniki Wrocławskiej.
57. Modelowanie ograniczeń w metodzie pracy potokowej10.22630/PNIKS.2017.26.2.19 ↗
58. Bladowski, S. (1970). Metody Sieciowe w Planowaniu i Organizacji Pracy, PWE Warszawa.
59. Application of a Technique for Research and Development Program Evaluation10.1287/opre.7.5.646 ↗
60. Kostrzewa-Demczuk, P., and Rogalska, M. (2020). Anticipating the Length of Employees’ Working Time. Symmetry, 12.10.3390/sym12030413 ↗
61. Planning of construction projects taking into account the design risk
62. Kostrzewa-Demczuk, P. (2022). Scheduling with TCM Methods in the Probabilistic Approach. [Ph.D. Thesis, Kielce University of Technology].