journal article·2020-07-28Open access

Estimation Method for TBM Cutterhead Drive Design Based on Full-Scale Tunneling Tests for Application in Utility Tunnels

Kyoungyul Kim, Jungjoo Kim, Heehwan Ryu, Hafeezur Rehman, Turab H. Jafri, Hankyu Yoo, Sanggui Ha

Applied Sciences· Volume 10· Issue 15

Abstract

The utility tunnels used for electricity transmission are in high demand these days. The literature presents many limitations in the currently used cutterhead drive design procedure while using a shield tunnel boring machine (TBM) for the excavation of these relatively small diameter tunnels. In order to develop an appropriate design method specially for cutterhead drive, experimental data obtained through the operation of a 3560 mm diameter shield TBM were used in this research work. For experimental purpose, an earth pressure balance (EPB) shield TBM was manufactured and a facility was established for performing the full-scale tunneling tests. Numerous tests were performed through the variation of TBM operational parameters such as thrust force and the rotational speed of the cutterhead at four UCS (Uniaxial compressive strength) levels of artificial rock mass. The relationships between thrust force and torque were mainly established and the effects of UCS and rotational speed of cutterhead on these relationships are analyzed through a representative case of 100 MPa UCS. A novel torque estimation method is also presented in this study which can be conveniently used in the cutterhead drive design while using small diameter shield TBMs.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Tunneling and Rock Mechanics · Advanced Surface Polishing Techniques · Drilling and Well Engineering

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Next Generation Transmission & Substation Laboratory, KEPCO Research Institute, 105 Munji-Ro, Yuseong-Gu, Daejeon 34056, Korea

Department of Civil and Environmental Engineering, Hanyang University, Sangnok–gu, Ansan 15588, Korea

NUST Institute of Civil Engineering, National University of Science and Technology (NUST), Islamabad 44000, Pakistan

Funding

Korea Electric Power Corporation

References (16)

Show source-provided references
1. Development of hybrid intelligent models for predicting tbm penetration rate in hard rock condition10.1016/j.tust.2016.12.009 ↗
2. A study of various models used in the estimation of advance rates for hard rock tbms10.1016/j.tust.2019.103219 ↗
3. Bruland, A. (2000). Hard Rock Tunnel Boring, Fakultet for Ingeniørvitenskap og Teknologi.
4. Rostami, J. (1997). Development of a Force Estimation Model for Rock Fragmentation with Disc Cutters through Theoretical Modeling and Physical Measurement of Crushed Zone Pressure. [Ph.D. Thesis, Colorado School of Mines Golden].
5. TBM perfomance estimation in rock using QTBM
6. Barton, N.R. (2000). Tbm Tunnelling in Jointed and Faulted Rock, CRC Press.
7. Bieniawski, Z., Celada, B., Galera, J., and Tardáguila, I. (2008). New Applications of the Excavability Index for Selection of Tbm Types and Predicting Their Performance, ITA World Tunneling Congress.
8. Bieniawski, Z., and Grandori, R. (2007). Predicting tbm excavability-part ii. Tunn. Tunn. Int.
9. Modeling tunnel boring machine performance by neuro-fuzzy methods10.1016/S0886-7798(00)00055-9 ↗
10. Grima, M.A., and Grima, M.A. (2000). Neuro-Fuzzy Modeling in Engineering Geology: Applications to Mechanical Rock Excavation, Rock Strength Estimation, and Geological Mapping, A.A. Balkema Rotterdam.
11. Hassanpour, J., Rostami, J., Firouzei, Y., and Tavakoli, H. (2019). Optimizing tbm cutterhead design for application in very strong and abrasive rocks, case study of kerman water tunnel. Tunnels and Underground Cities. Engineering and Innovation Meet Archaeology, Architecture and Art, CRC Press.10.1201/9780429424441-402 ↗
12. Applications of ntnu/sintef drillability indices in hard rock tunneling10.1007/s00603-012-0253-y ↗
13. A case study of tbm performance prediction using field tunnelling tests in limestone strata10.1016/j.tust.2018.10.001 ↗
14. A new hard rock tbm performance prediction model for project planning10.1016/j.tust.2011.04.004 ↗
15. Study of various models for estimation of penetration rate of hard rock tbms10.1016/j.tust.2012.02.012 ↗