Supporting Equipment Allocation for Multiple Projects in ERP Systems—Functionality Extension in IFS Applications
Source abstract
Abstract
Many organizations execute multiple projects simultaneously, competing for limited resources, including specialized and expensive equipment. Managing such multi-project environments requires advanced planning and decision-making. An additional difficulty is taking into account the possibility and profitability of using internal and external resources. The construction industry is a particularly demanding example of this scenario, where simultaneously executed projects must share high-value equipment with limited availability. Project management planning with resource allocation is supported by various types of IT tools. ERP (enterprise resource planning) systems are particularly useful in this regard, as they use the organization’s transaction data directly, but only offer basic project support. Therefore, it is necessary to extend their functionality in order to fulfill the expected functional requirements of business users, with particular emphasis on the provision of a consistent, graphically supported interface. This article proposes an algorithm to support decision-making on equipment allocation in a multi-project environment, taking into account the use of own and third-party equipment. A case study is presented demonstrating the practical implementation of the proposed solution in the IFS Applications ERP system. The developed extension supports users through graphical and numerical presentation of machine workloads across multiple projects.
Source: crossref · Quality: baseline
Research context
OpenAlex topics: ERP Systems Implementation and Impact · Business Process Modeling and Analysis · BIM and Construction Integration
SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.
Affiliations
InfoConsulting Poland Sp. z o.o., Grzybowska 2/36, 00-131 Warszawa, Poland
Department of Automatic Control and Robotics, AGH University of Krakow, al. Adama Mickiewicza 30, 30-059 Kraków, Poland
Funding
AGH University of Krakow
References (33)
Show source-provided references
1. Causes of miscommunication leading to project delays and low work quality in the construction industry of Saudi Arabia10.1016/j.asej.2023.102447 ↗
2. The mutual influence approach during the resource allocation process in construction projects10.1088/1757-899X/1030/1/012104 ↗
3. Benefits realisation in post-implementation development of ERP systems: A case study10.1016/j.procs.2021.01.186 ↗
4. Machine learning-driven optimization of enterprise resource planning (ERP) systems: A comprehensive review10.1186/s43088-023-00460-y ↗
5. Shang, S., and Seddon, P.B. (2000). A comprehensive framework for classifying the benefits of ERP systems. AMCIS 2000 Proceedings, Association for Information Systems.
6. A two-phase approach for solving the multi-skill resource-constrained multi-project scheduling problem: A case study in construction industry10.1108/ECAM-07-2019-0384 ↗
7. New summary measures and datasets for the multi-project scheduling problem10.1016/j.ejor.2021.10.006 ↗
8. Multi-project scheduling under uncertainty and resource flexibility: A systematic literature review
9. Resource-constrained multi-project scheduling problem: A survey10.1016/j.ejor.2022.09.033 ↗
10. A genetic algorithm with resource buffers for the resource-constrained multi-project scheduling problem10.1016/j.ejor.2023.11.009 ↗
11. A multi-agent based cooperative approach to decentralized multi-project scheduling and resource allocation10.1016/j.cie.2020.106961 ↗
12. A combined multi-agent system for distributed multi-project scheduling problems10.1016/j.asoc.2021.107402 ↗
13. Supply chain integrated resource-constrained multi-project scheduling problem10.1016/j.cie.2024.110380 ↗
14. Ghoroqi, M., Ghoddousi, P., Makui, A., Shirzadi Javid, A.A., and Talebi, S. (2023). An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms. Buildings, 13.10.3390/buildings13082023 ↗
15. Simultaneous scheduling of multiple construction projects considering supplier selection and material transportation routing10.1016/j.autcon.2022.104336 ↗
16. Time and finance optimization model for multiple construction projects using genetic algorithm10.1515/jmbm-2022-0032 ↗
17. Microsoft (2025, August 22). Project Management Goal: Resolve Resource Allocation Problems. Available online: https://support.microsoft.com/en-us/office/project-management-goal-resolve-resource-allocation-problems-cd56604a-f660-4ab2-b074-4cfafaef982d.
18. (2025, March 01). Best ERP Software. Available online: https://www.selecthub.com/erp-software/.
19. Design Science in Information Systems Research10.2307/25148625 ↗
20. Shirodkar, S. (2020). Learning Microsoft Project 2019: Streamline Project, Resource, and Schedule Management with Microsoft’s Project Management Software, Packt Publishing Ltd.
21. Increasing the potential application of Microsoft project and Primavera P6 for project management: A comparative analysis of the residential project10.1016/j.matpr.2022.11.485 ↗
22. Automated issue assignment using topic modelling on Jira issue tracking data10.1049/sfw2.12129 ↗
23. Asana and Trello: A comparative assessment of project management capabilities
24. White, K., Grierson, H., and Wodehouse, A. (2017, January 7–8). Using Slack for synchronous and asynchronous communication in a global design project. Proceedings of the 19th International Conference on Engineering and Product Design Education, Oslo, Norway.
25. Analysis of project management tools to support knowledge management10.1016/j.procs.2023.01.472 ↗
26. Panorama Consulting Group (2025, April 01). Top 10 ERP Software to Fulfill Your 2025 Goals. Available online: https://www.panorama-consulting.com/top-10-erp-software/.
27. (2025, April 22). Overview of Universal Resource Scheduling in Dynamics 365. Available online: https://learn.microsoft.com/pl-pl/dynamics365/field-service/rso-overview.
28. SAP SE (2025, April 22). Resource Scheduling–Features. Available online: https://www.sap.com/sea/products/scm/resource-scheduling/features.html.
29. SAPSE (2025, April 22). SAP S/4HANA Asset Management for Resource Scheduling. Available online: https://www.sap.com/products/scm/resource-scheduling.html.
30. All for One Poland (2025, April 22). Planowanie produkcji w SAP APO PP/DS. Available online: https://www.all-for-one.pl/pl/poradnik/planowanie-produkcji-w-sap-apo-ppds/.
31. SAP Help Portal (2025, April 22). Multiresource Scheduling: Application Help. Available online: https://help.sap.com/docs/SAP_MULTIRESOURCE_SCHEDULING/7a593796fb564c7a9e832b8b6a476863/45c005906c9e52f8e10000000a1553f7.html?version=10.8&locale=en-US.
32. (2025, April 22). Enterprise Resource Planning (ERP) Software Solutions. Available online: https://www.ifs.com/solutions/enterprise-resource-planning.
33. Fijas, M., Grobler-Dębska, K., Kucharska, E., and Bauer, W. (2023). Optimization and planning of equipment allocation on multiple projects-solution proposal in ERP system. Proceedings of the 2023 27th International Conference on Methods and Models in Automation and Robotics (MMAR), Międzyzdroje, Poland, 22–25 August 2023, IEEE.10.1109/MMAR58394.2023.10242491 ↗