Tunnel Boring Machine (TBM), as the most advanced construction equipment for rock tunnels, has been widely used in railway tunnel engineering, water conservancy tunnel engineering, urban rail engineering, coal mine roadway engineering, and other fields. However, the disadvantage of TBM lies in its poor adaptability to complex geological conditions, resulting in a significant reduction in tunneling efficiency and even major accidents due to improper TBM construction measures, especially in weak and fractured strata, which pose a great challenge to TBM construction. Therefore, it is necessary to study the key technologies of TBM construction in weak and fractured strata in order to improve the efficiency of TBM construction. Based on the background of the TBM construction of the Gaoligongshan Tunnel on the Southwest Darui Railway, this paper provides a reference for safe and efficient TBM excavation in weak and fractured areas through research on equipment, excavation parameter control, and construction measures.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Tunneling and Rock Mechanics · Drilling and Well Engineering · Rock Mechanics and Modeling

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

State Key Laboratory of Shield Machine and Boring Technology, Zhengzhou 450001, China

China Railway Tunnel Group Co., Guangzhou 511400, China

Xinjiang Erqis River Investment Development (Group) Co., Ltd., Urumqi 830002, China

Funding

the Science and Technology Innovation Plan of China Railway Tunnel Group · The Opening Subject of the State Key Laboratory of Shield Machine and Boring Technology

References (23)

Show source-provided references
1. Effect of adverse geological condition on TBM operation in Ghomroud tunnel conveyance project10.1016/j.tust.2008.12.006 ↗
2. A study on key construction techniques for tunnel boring machines adopted in super-long tunnels
3. Advances in tunnel boring machine application in China
4. Rockburst risk control for large diameter TBM boring in high geostress region
5. Study on TBM Type-selection and Key Technologies in Dahuofang Water Diversion Tunnel
6. The Research on Construction Technology of TBM Continuous Through the Limestone Section of No. 4 Bid of Songhua River Water Conveyance Project
7. Research on the selection of TBM equipment
8. Equipment selection and designation of TBM in long distance and large slope incline shaft of Xinjie Taigemiao mine
9. The development of the main driving device of Φ5m TBM
10. Analyses of the Geological Factors Effecting on Selecting Type of TBM
11. Retrospective analysis of TBM accidents from its poor flexibility to complicated geological conditions
12. Progresses, challenges and countermeasures for TBM construction technology in China
13. Prospects of key technologies of rock tunnel boring machine
14. Development and application of key technologies for TBM used in complex geological conditions
15. Study of key construction technologies of open TBM in complex geological conditions: Case study of Gaoligongshan tunnel
16. Performance prediction of hard rock tunnel boring machines (TBMs) in difficult ground10.1016/j.tust.2016.01.009 ↗
17. Hard rock TBM tunneling in challenging ground: Developments and lessons learned from the field10.1016/j.tust.2016.01.008 ↗
18. TBM tunnelling under adverse geological conditions: An overview10.1016/j.tust.2016.04.002 ↗
19. The Mechanism of TBM Shield Jamming Disaster Tunnelling through Deep Squeezing Ground
20. 3D Numerical Simulation of the Interaction between Rock Mass and Shield TBM Passing through the Fault Fracture Zone
21. Construction Technologies for Open TBM Used in Karst Areas and Soft-weak and Broken Grounds: Case Study of Songhua River Water Diversion Project
22. Development of TBM in Extremely Complex Geology and Key Technology of Efficient Construction
23. Research on Causes and Treatment Measures of Large-scale Collapse of Open Type TBM in Weak Stratum