The main feature of a prestressed concrete containment vessel (hereinafter referred to as “PCCV”) is that unbonded tendons, which are not bonded to the structure, are used because the tension of the tendon needs to be measured in periodical in-service inspection (hereinafter referred to as “ISI”) to ensure that the performance of the power plant is maintained during the service life. This report describes the results of measurement of the tension of the tendon, which has been performed as an activity to maintain the PCCV in Ohi Nuclear Power Plant (hereafter referred to as Ohi “NPP”) Units 3 and 4 of Kansai Electric Power in the past twenty some years since the construction of the PCCV, the changes in the standards and guidelines for the maintenance of the PCCV in Japan, as well as the discussion of non-destructive test-based methods for estimating the strength of high-strength concrete used for the PCCV and the development of a hydraulic shim-type load cell-based system for the measurement of the tension of the tendon, taking into account the ease of non-destructive testing, etc.
Source: openalex_inverted_index · Quality: baseline

Research context

OpenAlex topics: Structural Behavior of Reinforced Concrete · Concrete Corrosion and Durability · Geotechnical Engineering and Underground Structures

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Nuclear Power Division, The Kansai Electric Power Co.,Inc., Japan.

Nuclear Facilities Division, Obayashi Corporation, Japan.

Technical Research Institute, Obayashi Corporation, Japan.

Planning & Design Section, Nuclear Facilities Engineering II, Nuclear Facilities Division, Taisei Corporation, Japan.

Building System and Material Research Section, Building Engineering Research Institute, Technology Center, Taisei Corporation, Japan.

Wakasa Branch, The General Environmental Technos Co., Ltd., Japan.

References (5)

Show source-provided references
1. 1) Abe, T., Kawai, I., Ohashi, H., Murazumi, Y. and Takezaki, S., (2003). “New prestressing force meas¬urement system for prestressed concrete containment vessels.” SMiRT-17, August, Paper #H03-3.
2. 2) Ozaki, M., Kawai, I., Ohashi, H., Murazumi, Y. and Takezaki, S., (2002). “New prestressing force measurement system for prestressed concrete containment vessels.” The first fib Congress, Session 15, Monitoring, 233-238.
3. 3) Ozaki, M., Takeuchi, K. and Kitagawa, T., (2004). “Construction and maintenance of a Nuclear Power Plant Prestressed Concrete Containment Vessel (PCCV).” Journal of Prestressed Concrete, 46(6), 41-48. (in Japanese)
4. 4) Tsuzuki, M., Koshiro, Y., Fushimi, M. and Nakano, M., (2014). “Study on estimating strength of high strength concrete − Experimental studies of several non-destructive inspection for concrete and concrete core strength using mock-up mass concrete specimen at 5 years age −.” AIJ J. Technol. Des. 20(45), 487-490. (in Japanese)10.3130/aijt.20.487 ↗