Numerical Study on the Fully Mechanized Rapid Construction Method for Subsea Tunnel

Jian Ni, Xin Gao, Yuxue Chen, Hongliang Liu, Hui Cai, Wenfeng Tu

Publisher page

Abstract

ABSTRACT This paper presents a case study of a super‐long subsea tunnel in Jiaozhou Bay, Qingdao, China. To address key technical challenges in the fully mechanized rapid construction of super‐long subsea tunnels, this study systematically investigates the optimization of excavation methods and support installation distance across different rock grades by integrated numerical simulation and field monitoring. A numerical model was developed to analyze deformation response and stability under classes III, IV, and V surrounding rock conditions using both bench method and full‐face methods, supplemented by multi‐scenario construction step tests. Results indicate that the full‐face method is suitable for class III rock without strict support distance requirements, where lining can be applied based on monitoring data and construction plans; For class IV rock, the full‐face method is recommended in stable sections, while the bench method should be used in fractured zones, with initial support closure limited to ≤70 m and secondary lining to ≤250 m from the excavation face; For class V rock, the bench method is advised, with initial support closure within ≤60 m and secondary lining within ≤240 m from the excavation face. Field monitoring confirmed that surrounding rock deformation remained within design limits, and initial support performed effectively, validating the proposed methods and distance criteria. This study provides theoretical and practical guidance for fully mechanized construction in similar subsea tunnel projects.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Geotechnical Engineering and Analysis · Rock Mechanics and Modeling · Tunneling and Rock Mechanics

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

School of Qilu Transportation Shandong University Jinan Shandong China

Qingdao Guoxin Jiaozhou Bay Second Subsea Tunnel Co., Ltd Qingdao Shandong China

State Key Laboratory of Loeintelligent Manufacturing of Advanced Construction Machinery Shandong University Jinan Shandong China

(Qihe) New Materials and Intelligent Equipment Research Institute Shandong University Dezhou Shandong China

Funding

National Key Research and Development Program of China · Natural Science Foundation of Shandong Province

References (24)

Show source-provided references
1. 10.1016/j.cej.2025.16366210.1016/j.cej.2025.163662 ↗
2. 10.1002/dug2.1204410.1002/dug2.12044 ↗
3. C. H.Han Y. L.Bai W. J.Zhang J. C.Zhang H. F.Ma andW. Y.Li “Numerical Investigation on the Influence of Mesoscopic Deformation on Contact Area and Hydraulic Aperture to Fracture Seepage ” (2025):1–14 https://doi.org/10.1002/dug2.70028.10.2139/ssrn.4953346 ↗
4. 10.1016/j.jgsce.2025.20570710.1016/j.jgsce.2025.205707 ↗
5. 10.1016/j.tust.2021.10398910.1016/j.tust.2021.103989 ↗
6. 10.1016/j.tust.2023.10516110.1016/j.tust.2023.105161 ↗
7. 10.1016/j.compgeo.2025.10720310.1016/j.compgeo.2025.107203 ↗
8. 10.1016/j.tust.2022.10454710.1016/j.tust.2022.104547 ↗
9. 10.1016/j.tust.2025.10674210.1016/j.tust.2025.106742 ↗
10. 10.1016/j.tust.2018.10.00210.1016/j.tust.2018.10.002 ↗
11. 10.1007/s42452-025-07397-010.1007/s42452-025-07397-0 ↗
12. 10.3389/feart.2022.105211710.3389/feart.2022.1052117 ↗
13. 10.3389/feart.2024.143842510.3389/feart.2024.1438425 ↗
14. 10.1016/j.jrmge.2024.05.01910.1016/j.jrmge.2024.05.019 ↗
15. 10.3390/buildings1410329710.3390/buildings14103297 ↗
16. 10.1016/0886-7798(95)00017-S10.1016/0886-7798(95)00017-S ↗
17. 10.3390/sym1306106910.3390/sym13061069 ↗
18. 10.1016/j.tust.2021.10392010.1016/j.tust.2021.103920 ↗
19. 10.1016/j.undsp.2022.10.00510.1016/j.undsp.2022.10.005 ↗
20. 10.3390/infrastructures1003006810.3390/infrastructures10030068 ↗
21. 10.1016/j.autcon.2021.10371410.1016/j.autcon.2021.103714 ↗
22. 10.1016/j.sandf.2023.10135610.1016/j.sandf.2023.101356 ↗
23. 10.3390/su15191427810.3390/su151914278 ↗
24. Analytical Solution for Mechanical Properties of Tunnel Influenced by Longitudinal Pressure and Reinforced Steel Plate