Network Analysis for Projects with High Risk Levels in Uncertain Environments
Source abstract
Abstract
The critical path method is one of the oldest and most important techniques used for planning and scheduling projects. The main objective of project management science is to determine the critical path through a network representation of projects. The critical path through a network can be determined by many algorithms and is useful for managing, monitoring, and controlling the time and cost of an entire project. The essential problem in this case is that activity durations are uncertain; time presents considerable uncertainty because the time of an activity is not always easily or accurately estimated. This issue increases the need to use neutrosophic theory to solve the critical path problem. Real-world problems are characterized by a lack of precision, consistency, and completeness. The concept of neutrosophic sets has been introduced as a generalization of fuzzy, intuitionistic fuzzy, and crisp sets to overcome the ambiguity surrounding real-world problems. Truth-, falsity-, and indeterminacy-membership functions are used to express neutrosophic elements. This study was performed to examine a neutrosophic event-oriented algorithm for determining the critical path in activity-on-arc networks. The activity time estimates are presented as trapezoidal neutrosophic numbers, and score and accuracy functions are used to obtain a crisp model of the problem. An appropriate numerical example is then used to explain the proposed method.
Source: openalex_inverted_index · Quality: baseline
Research context
OpenAlex topics: Resource-Constrained Project Scheduling · Multi-Criteria Decision Making · Construction Project Management and Performance
SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.
References (22)
Show source-provided references
1. Lewis · Project Planning, Scheduling, and Control: The Ultimate Hands-on Guide to Bringing Projects in on Time and on Budget: The Ultimate Hands-on Guide to Bringing Projects in on Time and on Budget · 2010
2. Harrison · Advanced Project Management: A Structured Approach · 2017
3. Hinze · Construction Planning and Scheduling · 2004 · 228 · 229
4. Burke · Project Management: Planning and Control Techniques · 2013
5. Kerzner · Project Management: A Systems Approach to Planning, Scheduling, and Controlling · 2017
6. Neutrosophic association rule mining algorithm for big data analysis10.3390/sym10040106 ↗
7. Project scheduling under uncertainty using fuzzy modeling and solving techniques10.1016/j.engappai.2012.07.012 ↗
8. Fuzzy project scheduling system for software development10.1016/0165-0114(94)90211-9 ↗
9. A simple approach to fuzzy critical path analysis in project networks10.1016/j.apm.2007.04.009 ↗
10. Analysis of critical paths in a project network with fuzzy activity times10.1016/j.ejor.2006.06.053 ↗
11. An analytical method for finding critical path in a fuzzy project network
12. Fuzzy critical path for project network
13. An analytical method for finding critical path in a fuzzy project network
14. Critical path analysis in the network with fuzzy activity times10.1016/S0165-0114(00)00076-2 ↗
15. Applying fuzzy method for measuring criticality in project network10.1016/j.ins.2007.01.035 ↗
16. Fuzzy critical path problem for project network10.12732/ijpam.v85i2.4 ↗
17. A fuzzy multi-criteria approach for critical path definition10.1016/j.ijproman.2008.03.006 ↗
18. A new hybrid multi-criteria decision-making approach for location selection of sustainable offshore wind energy stations: A case study10.1016/j.jclepro.2020.124462 ↗
19. A neutrosophictheory based security approach for fog and mobile-edge computing10.1016/j.comnet.2019.04.018 ↗
20. Evaluation of sustainable hydrogen production options using an advanced hybrid MCDM approach: A case study10.1016/j.ijhydene.2020.10.232 ↗
21. Neutrosophic multi-criteria decision making approach for iot-based enterprises10.1109/ACCESS.2019.2908919 ↗
22. A novel heuristic simulation-optimization method for critical infrastructure in smart transportation systems10.1002/dac.4397 ↗